Set number

Number elements or sheets sequentially.

Ribbon location:
VP_LAYOUT > Sheets
Command:
SetSTT

1. Purpose

Renumbers the sequence column (STT) for a batch of sheets in one click, instead of typing every cell in the schedule by hand. Use it after duplicating sheets or reordering the set: the numbers rerun from the start you choose.

2. Quick video (≤ 2 minutes)

[Video in production — follow the steps below for now.]

3. Steps

  1. Select the sheets to number in the Project Browser, or select a sheet-list schedule sitting on a sheet. [image 01: selected sheets in the Project Browser]
  2. Click Set number in the VP_LAYOUT tab, Sheets panel (inside the sheet-number group).
  3. The Set STT dialog shows a start-number prompt (default 1) — type the first number and click OK. [image 02: start-number input dialog]
  4. The tool numbers the sheets consecutively from that start in the current order. Open the schedule to check the number run. [image 03: numbered STT column in the schedule]

4. Real-world example

12 freshly duplicated typical-floor sheets, STT column still blank. Select all 12 in the Project Browser, run the command, type 1, OK — the 12 sheets carry numbers 1 through 12, matching the floors.

5. Common errors

SymptomFix
"Select Sheets in the Project Browser or a Schedule on a Sheet before running"Nothing selected — select sheets (or a sheet-list schedule) first, then rerun
"Invalid start number"The box only takes integers zero and up — retype the number and click OK
"Schedule ... is not a Sheet List Schedule"The picked schedule is not a sheet list — pick the right sheet-list schedule, then rerun
"Schedule ... has no sheets to number"The sheet-list schedule filters everything out — check the schedule filters

6. See also

  • Duplicate sheets — duplicate the batch before numbering.
  • Create print set — bundle the numbered sheets into a set for printing.
  • To shift sheet numbers up or down in bulk (for example after inserting one floor), use the two sibling buttons in the same group: Increment number and Decrement number — select the sheets to shift and click; the tool adds or subtracts 1 from the numbers and reports the result.